Water catchment 2 – phase 2, day 4

21 11 2022

It’s finished!

In terms of pix and storytelling, that’s jumping the gun a bit, but I am so excited and proud of this project (as I am of all the projects we do in Spring Creek Basin for our mustangs), that it seemed appropriate to start with the best part of the news.

What follows – in this post and one more future post – are pix of the last two days of work that take this water-catchment project from nearly done to ready to catch snow and rain!

Early last week, Garth Nelson and Daniel Chavez sneaked out to the basin with the purlins needed to weld onto the I-beams and got started welding them into place. Wednesday – the day featured in these images – Mike Jensen and I joined them to start putting the propanel (metal) roof sheets into place and screwing them into place atop the purlins. Above, Mike puts the first screws in place to hold the first sheet down!

Garth and Mike align the front edges of the roof sheets – which will just overhang the gutter – and screw them into place while Daniel watches.

As the first roof sheets were laid down, Daniel and Garth returned to their partnership of setting the purlins in place and welding them to the I-beams.

Mike and I got the roof sheets up and screwed down pretty quickly and then would wait while Garth and Daniel methodically welded each purlin in place.

Mike had the yellow drill, and I had the red. … I was pretty fond of that little tool over the two days. 🙂 Note how the purlins face in different directions. Garth and Daniel did that on purpose. Because the purlins had some “bend” to them, they reasoned that alternating the directions of the purlins would increase stability. Mike and I, walking about and drilling on that roof, can attest to the stability!

The purlins met atop the I-beams, to which Daniel and Garth welded them.

As Daniel welded, Garth held his end of the purlin in place, and vice versa, as you can see a couple of pix above.

As always, the guys used their portable welder on the back of the truck. The propanel roof sheets were on the flatbed trailer, and Mike and I would lift a few of those to the roof at a time, then climb back up on the roof (using their second truck as our “ladder”) and screw them down.

Closing in on the end of the roof!

I was happy to grab photos while Mike and I waited for Garth and Daniel to weld their purlins.

And we found ways to fill our time and stay busy. That little walk-through gate will eventually allow us to access the “interior” of the water catchment – under the roof – to do any maintenance or attend to valves at the tanks, etc. The panel “fencing” will go up later. How do you attach hinges to round steel pipe?

The welders weld the hinges to the pipe, of course!

And so the ends wouldn’t stick out to catch an unwary mustang, Mike sawed them off. 🙂 Always thinking about the horses, these guys!

This view is from up the hill, “behind” the water catchment, looking down the hill. You can juuuuust see the trough at far right behind Daniel.

And about here is where Wednesday’s work ended.

Our weather has been sunny and cold (teens) in the early mornings, followed by highs in the 40s or so – warm enough when you’re working! And among the benefits, remember: No gnats! 😉

As Paul Harvey used to say – at the end of the story – “the rest of the story” will be coming soon!





For love of a place

20 11 2022

Every day is a day of thanksgiving in Spring Creek Basin. … Maybe we appreciate it just a little bit more when quiet is restored after a time of chaos. 🙂





Peace in the valley

19 11 2022

Again.





Fab

18 11 2022

Usually, I like to see at least one eye of the horse in the pic, even if it doesn’t always work out to get a nice catchlight. But Sundance’s fabulous forelock hides his eyes, even as it makes him look, well, Fabio-fabulous!





Fair mosey

17 11 2022

Skywalker with the kind, dark eyes and fair face. Just moseying to catch up with his pal on a nippy late-autumn evening.





Water catchment 2 – phase 2, day 3

16 11 2022

We may not have snow, but the temps are telling us that winter is nigh! Garth Nelson and Daniel Chavez were in the basin this week, working in the cold wind to get the first batch of purlins in place and welded to the I-beams. They said they saw more vehicles in the basin the last two days than in the last year. … Have I mentioned that third rifle season here is like Grand Central Station? … Fortunately, not for much longer; it’s over half an hour after sunset Friday.

Every little bit brings the project closer to completion!





Peace in the evening

15 11 2022

Three days down, four days to go.





Water catchment – phase 2, day 2 (more)

14 11 2022

As promised a few days ago, here are some more pix of the work on the newest water catchment in Spring Creek Basin. 🙂

You won’t ever catch our BLM guys sitting down on the job! As I mentioned in the last post about the project, the guys started by setting up the laser level to mark the heights of the steel pipes that will hold the I-beams, which will support the purlins, which will be topped by the roof, which will catch the rain and snow to fill the tanks to water the mustangs! So here, Garth Nelson is setting the laser in a place where it will be high enough to shoot over the tops of the tanks so the pipes can all be marked. Not sitting down so much as getting the eyeball view!

While Garth set up the laser level, Daniel Chavez held the little doohickey that caught the laser at the right height at all the pipes and marked the appropriate levels.

Measure many times and many ways before the final cut, goes the saying? Garth and Mike Jensen also ran string lines to ensure the levels.

Most of the pipes required a fair bit to be cut off, but this one needed just a little sliver. … It also was the pipe that started to alert the guys that something was amiss with the blade(s) on their nifty little saw – and this pic of Daniel using it gives a little better glimpse of that tool.

For those of you interested in such things, here’s another angle of one of the guys’ favorite tools. The “blade” is a band that goes around those black wheels on the underside of the tool. Usually, it saws through heavy “stem pipe” almost like a hot knife through butter (a bit slower, but steel is, after all, steel!), but the first couple-few blades they tried – brand new out of the package – were just dulling the teeth on the blades within minutes. NOT working. That’s what led to the double-tool whammy of using the grinder tool as well as this tool – and then finding the blade that worked, which worked for all the rest of the pipes.

Using the tractor to carry the heavy I-beams to set atop the pipes.

While Daniel got started welding the first I-beam to the pipes in the middle of the catchment structure, Garth finished cutting the pipes to height/length.

The welding process fascinates me …!

The A-team!

Sparks flying – another good reason to wait till cooler weather for the completion of the project. 🙂

Garth holds the I-beam steady and level while Daniel makes the first weld to hold it in place.

Garth finished the welding on the last beam.

Working in Spring Creek Basin does have the perks of fabulous scenery. 🙂

Next up should be welding the purlins atop the I-beams!





Pretty bright girl

13 11 2022

That eye! A spark of brightness in an otherwise *bright* fall day. 🙂

Temple, so lovely!





Water catchment – phase 2, day 2

12 11 2022

Work resumed this week on the water catchment in Spring Creek Basin’s northwest valley. We were ahead of the snow that came Wednesday, and although we had an absolutely beautiful day, it was windy. We joked that Wyomingites would consider it merely *breezy*. We did gratefully note that there were no gnats. 😉 By Wednesday (and even Tuesday afternoon as we left the basin), I thought maybe we shouldn’t have joked about the wind, as it got *really* strong. … But … no gnats. There’s always a silver lining!

Once we got out to the site, the guys used the laser level to start measuring the heights of the steel pipes to ensure they would level length-wise (across the hill) and sloping width-wise (down the hill). We all converged to mark them by laser level, string and tape-measure methods at the appropriate heights, then Daniel Chavez (front right) and Garth Nelson (on the step stool) started cutting while Mike Jensen (left) and I stood by to help. … But shortly, they realized there was a problem with the nifty cutting tool that Garth is using in the pic above: The blade wasn’t really getting the job done. And I’ll be the first to tell you that THAT tool is one of their favorite tools for the *usual* ease with which it cuts through that heavy steel pipe.

One of the greatest things about Spring Creek Basin is, of course, its distance off the beaten path. But that also makes it a far distance from things such as, say, shops that sell tools – including new/sharp saw blades that don’t go dull within moments!

But our guys are as resilient as they are creative and engineering-minded and hard working! One of the other tools they had was a grinder-type of thing. While it wasn’t quite the tool for the job, they did have a cutting disc that could slice into the pipes, to be followed by the bigger saw. So they did that for several pipes … changing blades on the bigger saw a few times. Then, finally, the last blade was the ticket. Garth still cut into each pipe at the appropriate mark, and Daniel finished them off.

Here, they worked together: Daniel had gotten most of the way through one of the pipes, and Garth returned with the grinder tool to get through the last little bit … and then …

Look out below!

When all the pipes were cut to the right length/height, it was time to bring in the little orange muscle – the tractor! Last year, you’ll remember that the guys welded the purlins to the pipes, then screwed down the roof sheets onto those. This time, they brought out five I-beams. Those are the step between the pipes and the purlins the guys added to this year’s project. The I-beams will give them a wider and steadier base on which to set/weld the purlins in the near future. But those suckers are much heavier than the purlins, so some mechanized muscle was needed.

The first beam went to the middle, then we worked outward from either end.

With the beam supported by the tractor, the guys were able to get the beam(s) in place atop the pipes. Then it was just a matter of shoving (!) the beams forward to the mark(s) Mike and I made so each had an overhang of a foot from the front pipes. Along the front of the tanks, just below the roof – soon – we’ll run the gutter.

Once the beams were in place atop the pipes, and the level and slope checked, Daniel welded them in place.

Daniel did most of the welding, but he had to leave early, so Garth donned the welding gear and finished the job. (How great is it to have not one handy welder but two!)

The day’s work started with some camera issues (in addition to those tool issues mentioned above), so I used my phone … then (fortunately) checked my camera again and noticed and corrected a couple of settings. The above are all from my phone (which did a respectable job!). I’ll process some of those camera pix to post soon – just because I love to highlight the good work our BLM guys do in support of our mustangs!

In the meantime …

From last week’s work ^ – note the pipes …

… to this week’s progress ^ – note the beams atop the pipes!

It’s all coming together. 🙂